SPARK PARK
Follow the building of our new
outdoor classrooms
CHECK IN OFTEN TO WATCH THE PROGRESS!!
|

Surveying is complete
Tuesday, July 21 |

Sidewalks are marked
Tuesday, July 21 |

Supplies are delivered
Tuesday, July 21 |
|

Backhoe begins work
Tuesday, July 21 |

Sidewalk takes shape
Wednesday, July 22 |

First of two outdoor rooms takes shape
Wednesday, July 22 |
|

Concrete pours before the rain does
Thursday, July 23 |

Protecting the new sidewalk
Thursday, July 23 |

The walls are getting higher
Thursday, July 23 |
|

Shoring up the walls
Thursday, July 30 |

Starting the second classroom
Thursday, July 30 |

More progress on the 2nd classroom
Friday, July 31 |
|

Filling in the walls with cement
Friday, July 31 |

Filling in walls with cement
Friday, July 31 |

One room nearly complete
Tuesday, Aug. 4 |
|

Pouring the floor of the 2nd room
Wednesday a.m., Aug. 5 |

The view from Mr. Barton's room - 2nd fl.
Classroom nearest the main entrance |

Also from Mr. Barton's view
Classroom nearest the library |
|

Mr. Stapley shows off the pergula posts
added today
Thursday, Aug. 6 |

Inside Tile - Aug. 31
 |

Outer Tile - Sept. 1 |
|

Installation of the roof begins
Tuesday, Sept. 8 |

Green roof completed
Friday, Sept. 11 |
Our Park is almost finished! On Saturday, Sept.
26, members of the Compassionate Service Society planted crepe myrtles
around the new outdoor classrooms. The trees were donated through the
Spark Park program. See photos of their hard work below and also on
YouTube:
http://www.youtube.com/watch?v=k8Iyzbhucug |
|

The pergula is completed - looks great!
Oct. 13, 2009 |
|
|
|